Project Overview

The Calder Park Drive level crossing removal project enters final phase with new road bridge completion over Sunbury Line, scheduled for July opening, enabling permanent closure of both Calder Park Drive and Holden Road level crossings.

Project Timeline

Milestone Date Duration
Road Closure June 21, 1am Initial closure
Construction 24/7 operations 32 days
Bridge Opening July 23, 6am Traffic activation
Holden Road Closure Late July Permanent
Project Completion Late July Full implementation

Implementation Strategy

Component Status Impact
Bridge Construction Final phase Traffic elevation
Level Crossing Removal planned Safety enhancement
Traffic Flow Optimization Congestion reduction
Road Network Reconfiguration Access improvement
Infrastructure Modern upgrade System efficiency


More Info 


Discover more from Construction Methodology

Subscribe to get the latest posts sent to your email.

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO

Discover more from Construction Methodology

Subscribe now to keep reading and get access to the full archive.

Continue reading