Custom invert culverts, the first of 45 that left the production facility in March 2021. These total custom units will form the base of a platform extension at Bellambi Railway Station, Wollongong – NSW, Australia
The client, Transport For Tomorrow, a joint venture between Laing O’Rourke and Transport NSW, required these units in an exceptionally tight time frame to meet a rail occupation deadline. Modcast Delivered.
Modcast received contracts for the next two stations, Thirroul and Wollongong.

Source : Link