Successful completion of the first floating wind turbine assembly for the Éoliennes Flottantes du Golfe du Lion (EFGL) pilot project, marking a significant milestone in France’s offshore renewable energy development.

Technical Specifications

Component Detail Significance
Turbine Capacity 10 MW Most powerful in France
Project Scale 3 turbines Pilot farm
Installation Type Floating platform Advanced technology
Global Ranking Highest capacity On floating foundation
Location Gulf of Lion Mediterranean Sea

Implementation Progress

Phase Status Next Steps
First Turbine Assembly complete Testing phase
Second Floater In port Awaiting assembly
Third Floater Arriving Channel entry
Storage Dedicated zone Port facility
Testing Commencing System verification

Key Project Elements

. Technical Achievement:

  • Complete turbine-floater integration
  • Highest capacity floating installation
  • Advanced assembly methodology
  • Testing protocol implementation

. Project Coordination:

  • Port authority collaboration
  • Lifting operations management
  • Ballasting procedures
  • Marine logistics

. Partner Integration:

  • Euroports (quayside coordination)
  • Mammoet (crane operations)
  • Vestas (turbine supplier)
  • Eiffage Métal (floater ballasting)

More Info

 


Discover more from Construction Methodology

Subscribe to get the latest posts sent to your email.

Leave a Reply

Ads Blocker Image Powered by Code Help Pro

Ads Blocker Detected!!!

We have detected that you are using extensions to block ads. Please support us by disabling these ads blocker.

Powered By
100% Free SEO Tools - Tool Kits PRO

Discover more from Construction Methodology

Subscribe now to keep reading and get access to the full archive.

Continue reading