The Rix Group has successfully completed a complex intersection upgrade at Camp Mountain Road and Samford Road in Ferny Hills, demonstrating efficient project delivery under challenging time constraints while preserving adjacent conservation areas.
Technical Specifications
| Component | Quantity | Implementation |
|---|---|---|
| Steel Mesh | 1,031m² | Surface stabilization |
| Shotcrete | 213m³ | Four-day application |
| Strip Drains | Full coverage | Drainage solution |
| Work Window | 4 hours daily | 9:00 AM – 1:00 PM |
| Conservation Area | Minimal impact | Environmental protection |